General Steps to Creating NXT Jobs of FUJI NXT Programming

FUJI NXT Intelligent Feeder With 15 inches Reel Holder 44mm UF01100 side b

This section provides a basic roadmap of procedures for creating jobs for the NXT based upon the different methods of entering data in the job.

These roadmaps listed are only for general reference and are only designed to help in the job creation process. There are cases when more or less steps are required depending on the situation.

The details for performing the unique NXT steps listed in the following procedures are in the following sections.

The name in the steps that are marked (NXT) are based on the name of that item in this manual. For details on procedures that are not marked (NXT), refer to the Fuji Flexa User Manual, Chapter 2. The procedure can be determined based upon the name of the corresponding step.

3.2.1 Starting by changing an existing job

Follow the steps below when changing a job that is currently complete for other machine types into a job with an NXT line. Generating recipes is not necessary for the NXT unless one wants to view reports. Because this job was already completed using other machines, panelizing, and importing data is not required.

1. Open the existing job.

2. Change the current line to the new NXT line. (NXT)

3. Enter the machine configuration and process data. (NXT)

4. Enter auto backup pin data. (NXT, only for equipped machines)

5. Change certain part data for the NXT. (NXT)

6. Assign marks to machines.

7. Line balance the work load. (NXT)

8. Optimize the job. (NXT)

9. Generate reports. (NXT)

3.2.2 Starting by manually entering sequence data

If no outside data files are available, it is possible to create a job completely through data entry. Follow the roadmap below to create a basic job through manual data entry.

Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Add a line to the job.

3. Enter the machine configuration and process data. (NXT)

4. Enter auto backup pin data. (NXT, only for equipped machines)

5. Import part data into the job or create part data in the job. (NXT)

6. Add parts.

7. Import mark data into the job or create mark data in the job.

8. Create mark sequences.

9. Assign marks to machines.

10.Panelize the panel (Panel Management).

11.Line balance the work load. (NXT)

12.Optimize the job. (NXT)

13.Generate reports. (NXT)

3.2.3 Starting by importing centroid CAD data

Follow the roadmap below to create a basic job by importing centroid CAD data.

Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the centroid CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Add a line to the job.

8. Enter the machine configuration and process data. (NXT)

9. Enter auto backup pin data. (NXT, only for equipped machines)

10.Panelize the panel (Panel Management).

11.Assign marks to machines.

12.Line balance the work load. (NXT)

13.Optimize the job. (NXT)

14.Generate reports. (NXT)

3.2.4 Starting by importing CCIMF files with part data

It is possible to create a job completely through importing generated CCIMF files with part data. Follow the roadmap below to create a job by importing CCIMF files with part data.

Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job by importing CCIMF data.

2. Change the current line to the new NXT line. (NXT)

3. Enter the machine configuration and process data. (NXT)

4. Enter auto backup pin data. (NXT, only for equipped machines)

5. Change certain part data for the NXT. (NXT)

6. Panelize the panel (Panel Management).

7. Assign marks to machines.

8. Line balance the work load. (NXT)

9. Optimize the job. (NXT)

10.Generate reports. (NXT)

3.2.5 Starting by importing MCSIMF files

It is possible to create a job completely through importing generated MCSIMF program and

part data files. Follow the roadmap below to create a job by importing MCSIMF files.

Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job by importing MCSIMF data.

2. Import the MCS part data into the job (only necessary if part data was not imported in step 1).

3. Change the current line to the new NXT line. (NXT)

4. Enter the machine configuration and process data. (NXT)

5. Enter auto backup pin data. (NXT, only for equipped machines)

6. Change certain part data for the NXT. (NXT)

7. Panelize the panel (Panel Management).

8. Assign marks to machines.

9. Line balance the work load. (NXT)

10.Optimize the job. (NXT)

11.Generate reports. (NXT)

3.2.6 Starting by importing Allegro CAD data

Follow the roadmap below to create a basic job by importing Allegro CAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the Allegro CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11.Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.7 Starting by importing Mentor CAD data

Follow the roadmap below to create a basic job by importing Mentor CAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the Mentor CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11.Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.8 Starting by importing CR5000 (PWS/Board Designer) CAD data

Follow the roadmap below to create a basic job by importing CR5000 CAD data.

Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the CR5000 CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11.Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.9 Starting by importing OrCAD CAD data

Follow the roadmap below to create a basic job by importing OrCAD CAD data. Generating

recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the OrCAD CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11.Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.10 Starting by importing SFX-J1 CAD data

Follow the roadmap below to create a basic job by importing SFX-J1 CAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the SFX-J1 CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11. Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.11 Starting by importing Specctra CAD data

Follow the roadmap below to create a basic job by importing Specctra CAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the Specctra CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11. Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.12 Starting by importing PowerPCB CAD data

Follow the roadmap below to create a basic job by importing PowerPCB CAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the PowerPCB CAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Perform a verify check

8. Add a line to the job.

9. Enter the machine configuration and process data. (NXT)

10.Enter auto backup pin data. (NXT, only for equipped machines)

11. Panelize the panel (Panel Management).

12.Assign marks to machines.

13.Line balance the work load. (NXT)

14.Optimize the job. (NXT)

15.Generate reports. (NXT)

3.2.13 Starting by importing PanaCAD data

Follow the roadmap below to create a basic job by importing PanaCAD data. Generating recipes is not necessary for the NXT unless one wants to view reports.

1. Create a job manually.

2. Import the PanaCAD data.

3. Import the BOM file.

4. Import any existing part data into the job.

5. Create any missing part data. (NXT)

6. Import mark data into the job.

7. Add a line to the job.

8. Enter the machine configuration and process data. (NXT)

9. Enter auto backup pin data. (NXT, only for equipped machines)

10. Panelize the panel (Panel Management).

11.Assign marks to machines.

12.Line balance the work load. (NXT)

13.Optimize the job. (NXT)

14.Generate reports. (NXT)